Security constrained robust unit commitment

Description
Robust formulations of the day-head unit commitment problem taking into account
  1. load variation (a6electr_ro_hdem.mos) represented via scenarios
  2. k contingencies (a6electr_ro_kcont.mos) represented via a 'cardinality' uncertainty set
Further explanation of this example: Whitepaper 'Robust Optimization with Xpress', Section 6 Robust unit commitment

roba6electr.zip[download all files]

Source Files
By clicking on a file name, a preview is opened at the bottom of this page.
a6electr_ro_hdem.mos[download]
a6electr_ro_kcont.mos[download]

Data Files





a6electr_ro_hdem.mos

(!******************************************************
   Mosel Example Problems
   ======================

   file a6electr_ro_hdem.mos
   ``````````````````````````
   Security constrained robust unit commitment under
   load variation. The present model produces a
   unit commitment schedule that does not require
   startup or shutdown change as long as the realized
   load is a convex combination of some historical
   load expressed with the 'scenario' uncertainty set.
  
   Features:
     - Using the 'scenario' uncertainty set
     - Unit commitment robust against load variaton

   Objectives:
     - Minimize expected running cost
     - No commitment modification if load varies

   What to look at:
     - The number of committed units per periods
     - The power generation reserve
     - The loss-of-load risk

   source: see a6electr.mos for the original formulation

   (c) 2014 Fair Isaac Corporation
       author: S. Heipcke, Mar. 2002
               S. Lannez, Mar. 2014
*******************************************************!)

model "A-6 Electricity production (robust)"
 uses "mmsystem", "mmrobust"
 
 declarations
  NT = 7                              ! Number of time periods
  TIME = 1..NT                        ! Time periods
  PLANTS = 1..4                       ! Power generation plant
  UNITS: set of string                ! Power generation units

  LEN, DEM: array(TIME) of integer    ! Length and demand of time periods
  PMIN,PMAX: array(PLANTS) of integer ! Min. and max output of a generator type
  CSTART: array(PLANTS) of integer    ! Start-up cost of a generator
  CMIN: array(PLANTS) of integer      ! Hourly cost of gen. at min. output
  CADD: array(PLANTS) of real         ! Cost/hour/MW of prod. above min. level
  PLANT: array(UNITS) of integer      ! Unit generation plant

  YEARS: range                        ! Historical years
  HDEM: array(YEARS,TIME) of integer  ! Historical demand profiles

  start: array(UNITS,TIME) of mpvar   ! Is generation unit starting ?
  work: array(UNITS,TIME) of mpvar    ! Is generation unit up ?
  padd: array(UNITS,TIME) of mpvar    ! Production above min. output level
 end-declarations
 
 initializations from 'a6electr_ro_simple.dat'
  LEN DEM PMIN PMAX CSTART CMIN CADD PLANT HDEM
 end-initializations 

 write("\n", strfmt("Unit type",-20))
 forall(p in PLANTS) write(strfmt(p,8),"   ")
 write("\n", strfmt("Pmax",20))
 forall(p in PLANTS) write(strfmt(PMAX(p),8),"  ")
 writeln
 writeln

!***************************Subroutines***************************
!**** Helper routine to create scenario uncertain set ****
  public procedure makescenario(a:array(r1:range,c1:range) of integer,
	  u:array(c2:range) of uncertain)
    declarations
      aa:dynamic array(r0:range,U:set of uncertain) of real  
    end-declarations  
    forall(i in r1, j in c1|exists(a(i,j)) and exists(u(j)),n as counter) do
      aa(n,u(j)):=a(i,j)
    end-do
    scenario(aa)
  end-procedure


!**** Robust against past scenario ****
 public procedure robust_demand
   declarations
     demand: array(TIME) of uncertain    ! Uncertain power demand
   end-declarations

  ! Add uncertainty set (time correlation)
   makescenario(HDEM,demand)

  ! Security reserve upward
   forall(t in TIME) sum(u in UNITS) PMAX(PLANT(u))*work(u,t) >= demand(t)

 end-procedure

!**** Print highest loss of load in case of worst case scenario realization
 procedure print_risk
   write("\n", strfmt("Loss of load",20))
   forall(t in TIME) do
     s:= sum(u in UNITS) (work(u,t).sol*PMAX(PLANT(u))) ! Total capacity
     v:= maxlist(DEM(t), max(y in YEARS) HDEM(y,t))     ! Hist. peak demand
     if(s < v) then 
       write(strfmt(v-s,8)) 
     else 
       write(strfmt("",8)) 
     end-if
   end-do
 end-procedure

!**** Solution printing ****
 procedure print_solution
   writeln("Total cost: ", getobjval)

   write(strfmt("Time period ",-20))
   ct:=0
   forall(t in TIME) do
     write(strfmt(ct,5), "-", strfmt(ct+LEN(t),2), "")
     ct+=LEN(t)
   end-do 

   write("\n",strfmt("Up Units",-20))
   forall(t in TIME) write(strfmt(sum(u in UNITS) work(u,t).sol,8))
   write("\n", strfmt("Gen. Pwr.",20))
   forall(t in TIME)
     write(strfmt(sum(u in UNITS) (work(u,t).sol*PMIN(PLANT(u))+padd(u,t).sol),8))
   write("\n", strfmt("Gen. Cap.",20))
   forall(t in TIME)
     write(strfmt(sum(u in UNITS) (work(u,t).sol*PMAX(PLANT(u))),8))
   write("\n", strfmt("Res. Dn",20))
   forall(t in TIME) write(strfmt(sum(u in UNITS) (padd(u,t).sol),8))
   write("\n", strfmt("Res. Up",20))
   forall(t in TIME)
     write(strfmt(sum(u in UNITS) work(u,t).sol*PMAX(PLANT(u)) - DEM(t),8))

   print_risk	    
   writeln	  
 end-procedure

!***************************Main model***************************
! Create decision variables
 forall(u in UNITS, t in TIME) do
  start(u,t) is_binary
  work(u,t) is_binary
 end-do

! Objective function: total daily cost
 Cost:= sum(u in UNITS, t in TIME) (CSTART(PLANT(u))*start(u,t) +
  LEN(t)*(CMIN(PLANT(u))*work(u,t) + CADD(PLANT(u))*padd(u,t))) 
                                   
! Number of generators started per period and per type
 forall(u in UNITS, t in TIME) 
  start(u,t) >= work(u,t) - if(t>1, work(u,t-1), work(u,NT))

! Limit on power production range
 forall(u in UNITS, t in TIME) 
  padd(u,t) <= (PMAX(PLANT(u))-PMIN(PLANT(u)))*work(u,t)

! Power balance
 forall(t in TIME) 
  sum(u in UNITS) (PMIN(PLANT(u))*work(u,t) + padd(u,t)) = DEM(t)

! Symmetry breaker
 forall(t in TIME, p in PLANTS) 
  forall(u1, u2 in UNITS | PLANT(u1) = PLANT(u2) and u1<u2) 
   work(u1,t) >= work(u2,t)

!**** Solving and solution reporting ****
! Solve the original problem
 minimize(Cost)

 writeln("\n=== Nominal case ===\n")
 print_solution

! Add robust constraints
 robust_demand

! Solve robust the problem
 setparam("ROBUST_UNCERTAIN_OVERLAP", true)
 minimize(Cost)

 writeln("\n=== Robust against demand variation ===\n")
 print_solution

end-model