Els - An economic lot-sizing problem solved by cut-and-branch and branch-and-cut heuristics Description The version 'ELS' of this example shows how to implement cut-and-branch (= cut
generation at the root node of the MIP search) and 'ELSCut' implements a
branch-and-cut (= cut generation at the MIP search tree nodes)
algorithm using the cut manager.
Source Files By clicking on a file name, a preview is opened at the bottom of this page.
ELS.cs // (c) 2023-2024 Fair Isaac Corporation using System; using Optimizer; using Optimizer.Objects; using static Optimizer.Objects.Utils; namespace XpressExamples { /// <summary>Economic lot sizing, ELS, problem</summary> /// <remarks> /// Solved by adding (l,S)-inequalities) in several rounds looping over /// the root node. /// /// ELS considers production planning over a horizon /// of T periods. In period t, t=1,...,T, there is a /// given demand DEMAND[t] that must be satisfied by /// production prod[t] in period t and by inventory /// carried over from previous periods. There is a /// set-up up cost SETUPCOST[t] associated with /// production in period t. The unit production cost /// in period t is PRODCOST[t]. There is no inventory /// or stock-holding cost. /// </remarks> class ELS { private static readonly double EPS = 1e-6; private static readonly int T = 6; /* Number of time periods */ /* Data */ private static readonly double[] DEMAND = { 1, 3, 5, 3, 4, 2 }; /* Demand per period */ private static readonly double[] SETUPCOST = { 17, 16, 11, 6, 9, 6 }; /* Setup cost / period */ private static readonly double[] PRODCOST = { 5, 3, 2, 1, 3, 1 }; /* Prod. cost / period */ private static double[,] D; /* Total demand in periods t1 - t2 */ /* Variables and constraints */ private static Variable[] prod; /* Production in period t */ private static Variable[] setup; /* Setup in period t */ /***********************************************************************/ private static void ModEls(XpressProblem p) { D = new double[T, T]; for (int s = 0; s < T; s++) for (int t = 0; t < T; t++) for (int k = s; k <= t; k++) D[s, t] += DEMAND[k]; // Variables prod = p.AddVariables(T) .WithType(ColumnType.Continuous) .WithName(t => $"prod{t + 1}") .ToArray(); setup = p.AddVariables(T) .WithType(ColumnType.Binary) .WithName(t => $"setup{t + 1}") .ToArray(); // Objective: Minimize total cost p.SetObjective( Sum( ScalarProduct(setup, SETUPCOST), ScalarProduct(prod, PRODCOST) ), Optimizer.ObjSense.Minimize ); // Constraints // Production in period t must not exceed the total demand for the // remaining periods; if there is production during t then there // is a setup in t // for all t in [0,T[ // prod[t] <= setup[t] * D[t][T-1] p.AddConstraints(T, t => prod[t].Leq(setup[t] * D[t, T - 1]).SetName($"Production_{t}") ); // Production in periods 0 to t must satisfy the total demand // during this period of time // for all t in [0,T[ // sum(s in [0,t+1[) prod[s] >= D[0][t] p.AddConstraints(T, t => Sum(t + 1, t => prod[t]).Geq(D[0, t]).SetName($"Demand_{t}") ); p.WriteProb("ELS.lp", "l"); } /**************************************************************************/ /* Cut generation loop at the top node: */ /* solve the LP and save the basis */ /* get the solution values */ /* identify and set up violated constraints */ /* load the modified problem and load the saved basis */ /**************************************************************************/ private static void SolveEls(XpressProblem p) { // Output all messages. p.callbacks.AddMessageCallback(DefaultMessageListener.Console); /* Disable automatic cuts - we use our own */ p.CutStrategy = (int)Optimizer.CutStrategy.None; /* Switch presolve off */ p.Presolve = (int)Optimizer.Presolve.None; int ncut = 0, npass = 0, npcut = 0; long starttime = Environment.TickCount64; double[] sol; do { p.WriteProb("model" + npass + ".lp", "l"); npass++; npcut = 0; // Solve the LP-problem p.LpOptimize(); if (p.SolStatus != Optimizer.SolStatus.Optimal) throw new Exception("failed to optimize with status " + p.SolStatus); // Get the solution values: sol = p.GetSolution(); // Search for violated constraints: for (int l = 0; l < T; l++) { double ds = 0.0; for (int t = 0; t <= l; t++) { if (prod[t].GetValue(sol) < D[t, l] * setup[t].GetValue(sol) + EPS) { ds += prod[t].GetValue(sol); } else { ds += D[t, l] * setup[t].GetValue(sol); } } /* Add the violated inequality: the minimum of the actual production prod[t] and the maximum potential production D[t][l]*setup[t] in periods 0 to l must at least equal the total demand in periods 0 to l. sum(t=1:l) min(prod[t], D[t][l]*setup[t]) >= D[0][l] */ if (ds < D[0, l] - EPS) { LinExpression cut = new LinTermMap(0); for (int t = 0; t <= l; t++) { if (prod[t].GetValue(sol) < D[t, l] * setup[t].GetValue(sol) + EPS) cut.AddTerm(prod[t]); else cut.AddTerm(setup[t] * D[t, l]); } p.AddConstraint((cut >= D[0, l]).SetName($"cut_{ncut + 1}")); ncut++; npcut++; } } Console.WriteLine("Iteration {0:d}, {1:f2} sec, objective value: {2:f}, cuts added: {3:d} (total {4:d})", npass, (Environment.TickCount64 - starttime) / 1000.0, p.ObjVal, npcut, ncut ); if (npcut == 0) Console.WriteLine("Optimal integer solution found:"); } while (npcut > 0); // Print out the solution: for (int t = 0; t < T; t++) { Console.WriteLine( "Period {0:d}: prod {1:f1} (demand: {2:f0}, cost: {3:f0}), setup {4:f0} (cost {5:f0})", t + 1, prod[t].GetValue(sol), DEMAND[t], PRODCOST[t], setup[t].GetValue(sol), SETUPCOST[t] ); } } public static void Main(string[] args) { using (XpressProblem prob = new XpressProblem()) { ModEls(prob); // Model the problem SolveEls(prob); // Solve the problem } } } } | |||||||||||||||||
© Copyright 2024 Fair Isaac Corporation. |